ENVIRONMENTAL IMPACT ASSESSMENT
Prior to project consent by the UK Government we are required to undertake
a detailed Environmental Impact Assessment (EIA). The initial EIA phase
involved completing a formal scoping report which identified the main
environmental sensitivities that could potentially be affected by our
Project, the extent of known environmental information and what additional
data gathering programmes would need to be carried out. The report was
issued in July 2004 to a wide range of stakeholders (150+) for review.
Comments were managed by the DTI who then produced a formal response,
these comments enabled our project team to modify the EIA process.
The
consultation process which began prior to EIA scoping will be continued
with all relevant parties throughout the project in order to ensure
that key environmental issues and sensitivities continue to be fully
understood and properly addressed.
The
EIA process
The EIAs purpose has been to identify and assess the potential impact
that our project could have, throughout its life (i.e. construction,
operations and decommissioning), on the surrounding physical, biological
and human environment, and where appropriate, advises on suitable measures
to reduce such impacts. In support of the process a wide range of information
gathering programmes have been completed, including:
|
|
Seabird
data gathering studies |
|
|
Subtidal
and intertidal benthic (faunal) studies |
|
|
Navigational
studies and collision risk assessment |
|
|
Reviews
of fish, shellfish and marine mammal ecology |
|
|
Review
of seabed and coastal processes |
|
|
Review
of socio-economic impacts |
|
|
Visual
assessment studies |
|
|
Terrestrial
habitat studies |
The
Environmental Statement
The Environmental Statement (ES) is the report that documents the
EIA process. Our ES has now been completed and was formally submitted
to the UK government on 8th July 2005. All stakeholders that could be
potentially affected will be given a change to review the ES and respond
formally to the regulator.